Articles

Timing Rules for Carrying Out Renovation

 

The Housing  Development Board of Singapore is strictly implementing timing rules for any form of renovation that needs to be carried out.

·         General renovation works must be carried out  between 8:00 am to 6 pm daily.

·         Heavy renovation works that creates a lot of noise such as wall demolitions, removing of floor finishes, cutting of tiles and drilling works must be done between 9:00 am to 6 pm on weekdays only.

·         During Public Holidays, Saturdays and Sundays, noisy renovation works are not allowed.

The renovation work must be completed within 1 month for old flats and 4 months for newly build flats. One the renovation is completed, home owners must inform the HDB Branch handling their flats.

 

Reference

http://www.hdb.gov.sg